Pleasant Gap (Pleasant Gap, PA)

Plant Name:

Plant Phone Number:
Sales Phone Number:

Address:


GPS Co-ordinates:


Pleasant Gap

1 814 357 4500
1 814 357 4500


965 East College Avenue
Pleasant Gap, PA 16823


Latitude:     40.89167
Longitude: -77.70883


  Map & Driving Directions
   Products Produced :
  High Calcium Quicklime
  High Calcium Hydrated Lime
  High Calcium Limestone Fines
  Screened High Calcium Limestone
  Pulverized High Calcium Limestone
  Lime Kiln Dust (Co-Products)
  Ag-Lime

Detailed Description:

Graymont is one of the leading suppliers of lime in the northeastern United States. Graymont currently operates three plants in Central Pennsylvania; however, all of these plants will be consolidated at Pleasant Gap where a major expansion project is underway.

Graymont's expansion project currently underway includes a 1,200 ton per day rotary lime kiln designated as Kiln #6, which is shown here. A new hydrating plant is included as part of this facility.

A second rotary lime kiln, designated as Kiln #7, is currently under construction. The new kiln will produce 1,050 tons of quicklime per day and will include a highly efficient emissions scrubbing system along with power generation from a waste heat recovery system (see photos of construction progress below).

We provide bulk product storage capacity and a multi-mode shipping capability that assures when Graymont customers place an order, it will be quickly shipped by rail or truck.

CONSTRUCTION PHOTOS - KILN #7

October 17, 2007 – Kiln #7 nears completion. New Kiln #6 on left.


April 20, 2007 - Kiln #7 - feed end support pier, waste heat recovery and emissions scrubbing structure, and power generation building

April 20, 2007 – Kiln #7 - concrete support piers, new kiln #6 on left

March 9, 2007- sections of kiln #7 to be assembled, kiln #7
discharge pier and lime cooler pit, new kiln #6 on right.